Explore the largest solar farms expected to come online in Oklahoma and see all proposed solar projects on a map.
Last updated: May 2026
On this page, you can explore our database of planned solar farms in Oklahoma. Each month, we track projects in development and update our list of the largest solar farms expected to come online in Oklahoma.
As of May 2026, there are 58 solar farms in development in Oklahoma, according to Cleanview's project tracker. Their total planned capacity is 10,361 MW. See also: operating solar farms in Oklahoma→
Planned Projects
58
Planned Capacity
10,361 MW
Unique Developers
16
Map of planned solar farms in Oklahoma. Marker size reflects planned capacity.
500 MW
Expected Online: November 2028
Location: Comanche, Oklahoma
Developer: Hecate Energy
400 MW
Expected Online: December 2027
Location: Muskogee, Oklahoma
Developer: NextEra Energy
390 MW
Expected Online: December 2030
Location: Muskogee, Oklahoma
350 MW
Expected Online: May 2030
Location: Johnston, Oklahoma
300 MW
Expected Online: June 2028
Location: Caddo, Oklahoma
Developer: Invenergy
300 MW
Expected Online: June 2031
Location: Muskogee, Oklahoma
Developer: Invenergy
300 MW
Expected Online: December 2030
Location: Atoka, Oklahoma
288 MW
Expected Online: December 2028
Location: Woodward, Oklahoma
Developer: Doral Renewables
252 MW
Expected Online: December 2026
Location: Grady, Oklahoma
Developer: NextEra Energy
125 MW
Expected Online: June 2026
Location: Mayes, Oklahoma
Developer: Leeward Energy
125 MW
Expected Online: June 2026
Location: Mayes County, Oklahoma
Developer: Leeward Energy
85 MW
Expected Online: June 2026
Location: Choctaw, Oklahoma
Developer: Shell
73 MW
Expected Online: June 2026
Location: Mayes, Oklahoma
Developer: Leeward Energy
102 MW
Expected Online: August 2026
Location: Mayes County, Oklahoma
Developer: Leeward Energy
200 MW
Expected Online: September 2026
Location: Grady, Oklahoma
Developer: TED Renewables
200 MW
Expected Online: September 2026
Location: Coal, Oklahoma
Developer: TED Renewables
191 MW
Expected Online: September 2026
Location: Lincoln, Oklahoma
Developer: TED Renewables
102 MW
Expected Online: September 2026
Location: Mayes, Oklahoma
Developer: Leeward Energy