Clean Energy and Storage
Project Tracker
We pull every major interconnection queue each day, then find the company developing each project.
- Planned solar
- 578 GW
- Planned battery storage
- 470 GW
- Planned wind
- 162 GW
- Developers identified
- 410
See which projects are likely to get built
Most projects in a queue never get built. A signed interconnection agreement is the best sign that one will: the developer has made it through the grid operator’s studies and agreed to pay for the upgrades it needs.
We track where every project stands in its queue. 54% of planned solar in the seven major queues has a signed agreement, from 79% in MISO to 42% in PJM.
MISO has the most planned solar with a signed interconnection agreement
Planned solar in each market's interconnection queue, GW
Find the developer behind every project
Four of the seven major queues don’t name a project’s developer. MISO lists the substation it connects to. ERCOT lists the company that filed, usually a project LLC like S&S Renewables, LLC.
We trace each project to the company building it, through interconnection agreements, FERC filings, state permits and developers’ own announcements. So far we’ve matched 3,321 planned projects to 410 developers.
| What the queue says | What you see in Cleanview | ||||
|---|---|---|---|---|---|
| Queue | Project | Company listed | Developer | Capacity | Interconnection agreement |
| MISO | J1060West Memphis - Keo 500 kV Line Tap, St. Francis County, Arkansas | None | Invenergy | 500 MW solar | Signed |
| PJM | AG1-125Marysville-Flatlick 765 kV, Madison County, Ohio | None | Savion | 400 MW solar | Signed |
| SPP | GEN-2021-070Hodgeman and Ford counties, Kansas | None | Engie | 504 MW wind | Signed |
| ERCOT | 26INR0155Ross Solar, Refugio County, Texas | S&S Renewables, LLC | Intersect Power | 1,026 MW solar | Signed |
| ERCOT | 24INR0258Zeissel Solar, Knox County, Texas | ZSS Power, LLC | NextEra Energy | 452 MW solar | Signed |
| ERCOT | 24INR0201Short Creek Solar, Wichita County, Texas | Wichita Solar I, LLC | TotalEnergies | 628 MW solar | Signed |
NextEra Energy and Invenergy have the most planned solar
Planned solar, GW, and the number of projects, top 10 developers
See every developer's pipeline
Each developer gets a profile with every project we’ve tied to it: where it’s filing, how big each project is, how far along it is in the queue and when it expects to come online.
NextEra Energy has 105 planned solar projects in 21 states. 83% of that capacity has a signed interconnection agreement.
Know the day a project moves
We check every queue each day and the EIA’s survey of planned plants each month. When a project enters a queue, signs its interconnection agreement or starts construction, it shows up in your feed.
Follow a developer, a market or a technology, and get the changes by email every day or every week.
Recent milestones
Solar, wind and storage projects of 100 MW or more
- October 26, 2026
Interconnection agreement
Heart Pine Solar, 150 MW solar
The AES Corporation. Marion County, Georgia. FERC
- October 26, 2026
Interconnection agreement
Sweet Magnolia Solar & Storage, 165 MW hybrid - solar + storage
The AES Corporation. Hancock County, Georgia. FERC
- October 26, 2026
Construction started
Keystone-DeSoto 345 kV, 100 MW wind
RWE. Blackford County, Indiana. PJM queue
- October 26, 2026
Construction started
Bottlebrush Solar, 200 MW solar
Invenergy. Lake County, Indiana. PJM queue
- October 24, 2026
Construction started
Lupinus Solar 1, LLC, 165 MW solar
Sunraycer Assets. Franklin County, Texas. EIA-860M
- October 23, 2026
Interconnection agreement
Hickory Creek, 221 MW wind
Apex Clean Energy. Nowata County, Oklahoma. FERC
Built for the companies that build, fund and supply projects
The same data answers different questions, depending on where you sit.
Developers
See where competitors are filing, how big their projects are and how far along each one is. Spot the counties and markets getting crowded before you file.
- Who else is building storage in my county?
- Which competitors signed agreements this quarter?
Investors
Size a developer's pipeline before a deal, and see how much of it is likely to get built. Track a market's buildout from queue to construction.
- How much of this developer's pipeline has an agreement?
- How much solar will MISO add by 2029?
Equipment makers and service providers
Find projects that will soon buy panels, batteries, turbines, transformers or construction services, and the developer to call.
- Which projects signed agreements in Texas this month?
- Who's developing the biggest projects in PJM?
Get our data through an API
Everything on this page comes through our API: each project’s capacity, status, location, developer and interconnection agreement, updated every day. Pull it into your models, your CRM or your GIS. Or download any table as a CSV.
GET /api/v1/projects?technology=Solar&status=Planned&developer=NextEra { "project_name": "MRR Solar", "developer": "NextEra Energy", "technology": "Solar", "capacity_mw": 500, "status": "Planned", "has_ia_signed": true, "operating_date": "2030-07-01", "county": "Pecos", "state": "TX", "source_table": "ercot_queue", "source_id": "30INR0053", ... }