Explore operating and planned data center projects in Virginia.
Last updated: June 2026
There are 371 operating data centers in Virginia with a combined capacity of 17,440 MW, and 422 planned projects that would add 39,078 MW of additional capacity. Explore the map and tables below for details.
Total Data Centers
799
Operating Data Centers
371
Planned Data Centers
422
Operating Capacity
17,440 MW
Planned Capacity
39,078 MW
Unique Developers
140
Map of data centers in Virginia. Blue markers indicate operating facilities and orange markers show planned projects. Marker size reflects capacity — only facilities with reported capacity data are shown.
243 MW
Year Operational: 2019
Location: Loudoun, Virginia
Developer: Digital Realty
202 MW
Year Operational: 2019
Location: Loudoun, Virginia
Developer: CyrusOne
189 MW
Year Operational: TBD
Location: Loudoun, Virginia
Developer: CloudHQ
189 MW
Year Operational: TBD
Location: Loudoun, Virginia
Developer: CloudHQ
177 MW
Year Operational: 2025
Location: Manassas City, Virginia
Developer: Digital Realty
175 MW
Year Operational: 2020
Location: Loudoun, Virginia
Developer: Digital Realty
168 MW
Year Operational: 2026
Location: Loudoun, Virginia
Developer: Cologix
163 MW
Year Operational: 2023
Location: Loudoun, Virginia
Developer: Aligned
143 MW
Year Operational: 2025
Location: Loudoun, Virginia
Developer: Aligned
2,400 MW
Expected Year: TBD
Location: Hanover, Virginia
Developer: Tract
2,100 MW
Expected Year: TBD
Location: Stafford, Virginia
Developer: Garrett Development Corporation
1,300 MW
Expected Year: TBD
Location: Loudoun, Virginia
Developer: Active Infrastructure
1,200 MW
Expected Year: TBD
Location: King George, Virginia
Developer: Oasis Digital Properties
1,100 MW
Expected Year: TBD
Location: Louisa, Virginia
Developer: EdgeCore
1,100 MW
Expected Year: 2027
Location: Stafford, Virginia
Developer: Stack Infrastructure
1,085 MW
Expected Year: TBD
Location: Henrico, Virginia
Developer: QTS
1,000 MW
Expected Year: 2027
Location: Stafford, Virginia
Developer: Stack Infrastructure
900 MW
Expected Year: 2027
Location: Caroline, Virginia
Developer: CleanArc Data Centers