Explore operating and planned data center projects in Georgia.
Last updated: July 2026
There are 39 operating data centers in Georgia with a combined capacity of 2,492 MW, and 128 planned projects that would add 11,851 MW of additional capacity. Explore the map and tables below for details.
Total Data Centers
169
Operating Data Centers
39
Planned Data Centers
128
Operating Capacity
2,492 MW
Planned Capacity
11,851 MW
Unique Developers
54
Map of data centers in Georgia. Blue markers indicate operating facilities and orange markers show planned projects. Marker size reflects capacity — only facilities with reported capacity data are shown.
268 MW
Year Operational: 2026
Location: Fayette County, Georgia
Developer: QTS
260 MW
Year Operational: 2025
Location: Fayette County, Georgia
Developer: QTS
173 MW
Year Operational: 2025
Location: Fayette County, Georgia
Developer: QTS
158 MW
Year Operational: 2026
Location: Fayette County, Georgia
Developer: QTS
158 MW
Year Operational: 2019
Location: Douglas, Georgia
Developer: Google
142 MW
Year Operational: 2023
Location: Whitfield, Georgia
Developer: Core Scientific
108 MW
Year Operational: 2026
Location: Fulton County, Georgia
Developer: EdgeConneX
103 MW
Year Operational: 2025
Location: Douglas County, Georgia
Developer: Aligned Data Centers
89 MW
Year Operational: 2007
Location: Douglas, Georgia
Developer: Google
1,400 MW
Expected Year: TBD
Location: Early, Georgia
Developer: QTS
1,250 MW
Expected Year: TBD
Location: Irwin, Georgia
Developer: Premier Data Center Development
900 MW
Expected Year: 2036
Location: Coweta, Georgia
Developer: Prologis
900 MW
Expected Year: TBD
Location: Twiggs, Georgia
Developer: Eagle Rock Partners LLC
600 MW
Expected Year: 2030
Location: Muscogee, Georgia
Developer: Habitat Partners
450 MW
Expected Year: 2030
Location: Spalding, Georgia
Developer: Industrial VI Enterprises / Hillwood
400 MW
Expected Year: 2029
Location: McDuffie, Georgia
Developer: Williams Brothers Development
400 MW
Expected Year: TBD
Location: Troup, Georgia
Developer: Google
300 MW
Expected Year: 2030
Location: Coweta, Georgia
Developer: T5 Data Centers