On this page, you can explore our database of planned battery storage projects in CAISO. Each month, we track projects in development and update our list of the largest battery storage projects expected to come online in CAISO.
As of September 2026, there are 400 battery storage projects in development in CAISO, according to Cleanview's project tracker. Their total planned capacity is 119,459 MW. See also: operating battery storage projects in CAISO→
Planned Projects
400
Planned Capacity
119,459 MW
Unique Developers
42
2,171 MW
Expected Online: March 2028
Location: La Paz, Arizona
Developer: Hanwha Group
1,176 MW
Expected Online: September 2032
Location: Merced, California
1,175 MW
Expected Online: September 2028
Location: Fresno, California
1,173 MW
Expected Online: September 2028
Location: Kern, California
1,170 MW
Expected Online: September 2028
Location: Fresno County, California
1,168 MW
Expected Online: December 2028
Location: Fresno, California
1,150 MW
Expected Online: December 2028
Location: Los Angeles, California
1,150 MW
Expected Online: July 2027
Location: Fresno, California
Developer: Intersect Power
1,150 MW
Expected Online: September 2033
Location: Imperial, California
300 MW
Expected Online: October 2026
Location: Fresno, California
Developer: NextEra Energy
80 MW
Expected Online: October 2026
Location: Merced, California
Developer: Peninsula Clean Energy
75 MW
Expected Online: November 2026
Location: San Bernardino, California
672 MW
Expected Online: December 2026
Location: Kern, California
236 MW
Expected Online: December 2026
Location: Clark, Nevada
Developer: NextEra Energy
184 MW
Expected Online: December 2026
Location: Fresno, California
Developer: EDP Renewables
114 MW
Expected Online: December 2026
Location: Alameda, California
Developer: Ignis
113 MW
Expected Online: December 2026
Location: Kern, California
Developer: Avantus
102 MW
Expected Online: December 2026
Location: Fresno, California